The Government, in July 2014, had announced tripling of the then existing capacity of 4780 MW in the next ten years. With the commencement of commercial operation of Kudankulam Nuclear Power Project (KKNPP), Unit-1 (1000 MW) in December 2014, the installed nuclear power capacity in the country has reached 5780 MW. In addition, KKNPP, Unit-2 (1000 MW) has been connected to the grid for the first time in August-2016 and is presently generating infirm power. On commencement of commercial operation of KKNPP-2, the installed nuclear power capacity in the country will reach to 6780 MW.
Further, four reactors with a total ....